A) Down Payment Plan
%Age
1. At the time of Booking 5%
2. Within 45 Days from date of Booking
(Less Down Payment rebate @14% on 90%)
90%
3. At the time of offer of Possession 5%
B) Construction Linked Interest Free Installment Plan
1. At the time of Booking 5%
2. Within 60 days from date of booking 7.5%
3. Within120 days from date of booking 7.5%
4. Within 180 days from date of booking 7.5%
5. On Start of Excavation of Tower in which unit is booked 7.5%
6. On Completion of Basement Roof Slab of Tower in which unit is
booked/ on Completion of foundations for Non –basement Towers
7.5%
7. On Completion of Third Floor Roof Slab of Tower 7.5%
8. On Completion of Sixth Floor Roof Slab of Tower 7.5%
9. On Completion of ninth Floor Roof Slab of Tower 7.5%
10. On Completion of Super structure framework 7.5%
11. On Completion of Brickwork 7.5%
12. On Completion of Internal Plumbing/Wiring Works 5%
13. On Completion of Flooring & Tiles 5%
14. On fixing of windows & doors shutter’s of unit 5%
15. At the time of offer of Possession 5%
* The Construction linked stages can be called for payment in any sequence, depending on the
sequence undertaken by the Developer, irrespective of the sequence mentioned hereinabove. Annexure-3.1
SCHEDULE OF PAYMENT –II
PAYMENT SCHEDULE OF FIRE FIGHTING CHARGES,
ELECTRIC CONNECTION CHARGES, POWER BACKUP CHARGES & EDC
1. On Completion of Internal Plumbing/Wiring Works 25%
2. On Completion of Flooring & Tiles 25%
3. On fixing of windows & doors shutter’s of unit 25%
4. At the time of offer of Possession 25%
PAYMENT SCHEDULE OF CAR PARKING CHARGES
1. On Completion of Internal Plumbing/Wiring Works 25%
2. On Completion of Flooring & Tiles 25%
3. On fixing of windows & doors shutter’s of unit 25%
4. At the time of offer of Possession 25%
PAYMENT SCHEDULE OF CLUB MEMBERSHIP
1. At the time of offer of Possession 100%